Customer: Alkermes
Location: Wilmington, OH
Alkermes is a pharmaceutical manufacturing facility located in Wilmington, OH. The multi-phase project consisted of a clean steam generator and associated distribution piping which included over 2,000 feet of orbitally welded stainless steel piping. The project also included 1,000 feet of WFI (Water for Injection) piping that was also an orbitally welded system. The final phase of work final involved connections to process equipment serving their production equipment. The project also required 142 tie-ins to multiple existing services over three shutdowns during the duration of the project.